Norocholai Power Station

Norocholai Coal Power Station
Location of Norocholai Coal Power Station
Country Sri Lanka
Location Norocholai, Puttalam
Coordinates
Status Operational
Construction began May 11, 2006 (2006-05-11)
Commission date March 22, 2011 (2011-03-22)
Construction cost US$ 1,350 million
Operator(s) Ceylon Electricity Board
Constructor(s) CMEC
Power station information
Primary fuel Coal
Combined cycle? Yes
Power generation information
Installed capacity 300 MW
Maximum capacity 900 MW
Annual generation 1,658 GWh

The Norocholai Power Station (also known as the Lak Vijaya Power Station) is a large coal-fired power station in Norocholai, Puttalam, Sri Lanka. Construction of the 900 MW facility was segmented into three 300 MW phases, officially beginning on May 11, 2006 (2006-05-11).[1]

The first 300 MW block was ceremonially commissioned by President Mahinda Rajapaksa on March 22, 2011 (2011-03-22) at 18:27 local time, with the presence of Minister of Energy Champika Ranawaka, deputy Minister of Energy Premalal Jayasekara, and Minister of Public Administration W. D. J. Senewiratne,[2] whose vehicle collided with a bus while arriving at the opening ceremony, causing minor injuries to both the minister and his driver.[3][4]

After the completion on the latter stages in 2013, it would surpass all power stations and rank as the largest power power producing body in the country, at 900 MW. This record is expected to be broken by the 1,000 MW Sampur Coal Power Station, to be commissioned in 2014.

According to the Ceylon Electricity Board, this US$455 million first phase would be able to generate nearly 1.7 TWh of energy annually upon completion in 2013; a major milestone in meeting the growing energy demand.[1] The plant will be connected to the grid via 115 km (71 mi) long 220-kilovolt transmission line. Power station exhausts are emitted through 150 m (492 ft) tall chimneys, one of the country's tallest man-made structures.[1]

Contents

Environmental impact

During its pre-development stages, numerous protests were carried out by residents living near the project site, claiming that they were deceived by the government.[5] The power station risks several negative factors including:

According to the Ministry of Power and Energy, some of these issues have now been solved.

October 2010 fire

A large fire had broken out on October 24, 2010. According to the Ceylon Electricity Board, there were no casualties. The Ministry of Power and Energy commented that damages to the facility would be borne by the constructors, and not the government or the developers.[6]